EDIT - Now a 'work at the local school' mum a few days a week while juggling the job of parenting 3 teenagers! I am a SAHM who does work from home occasionally, dedicated to raising 3 Godly, independent, healthy children. Loving the home building process though it is not without challenges. I have fairly free reign over the creative aspect of the project...just not the financial side!

Friday, August 30, 2013

Uneven to your eyes too??


Hmmmmm, a little uneven, I think. Can't wait to meet Matt on site next week to check out all the other hardware items that have been installed since my last visit.

Thursday, August 29, 2013

Update on laundry shelving error


Half of the laundry cupboard shelving

Well, it has been an 'exciting' few days in my neck of the woods. I received a Building Variation from EBH to delete 1/4 of the shelving that was erroneously installed. (You may remember, we had it deleted from the contract so we could do a custom fitout to suit our needs) Imagine my surprise when we were charged nearly $700 for the privilege of taking some of it out and adding an end panel in. Surprise was the nice word for it. No explanation via phone call, just an email with a $700 price tag. I asked for clarification  - if I delete the entire amount of shelving, would I be charged anything? NO was the answer! So essentially, I was either being charged $700 for ONE panel of melamine or EBH were trying to recoup the costs of their mistake by charging me for the shelving. A very sour taste has been left in my mouth on this one even though yes, I am getting free shelving (not quite what I want though). After asking a few questions, the Estimating Department has flipped their decision and there will be no charges to cut out 1/4 of the shelving. Yet another mistake, this time not handled well.

On a brighter note, the Temporary Supervisor rang for a chat today - lovely guy. Matt gave me a rundown on what is being done currently and about to happen with the house. The main floor tiles have been delayed further and will now commence early next week. The bath wall mixers will be changed over to the basin wall mixers a little later when the plumbers need to return for something else. Matt reassured me that work will continue smoothly in Troy's absence and will be scheduled ahead for Troy's return. I will try to meet up with him at the house on Monday morning sometime to have another look/see. Before then, I want to go through the contract to see if there is anything we added or deleted, check door handles, towel rails/rings etc, outside taps etc.

Friday, August 23, 2013

And he is OFF!

On holidays! I wish him all the sun and sand that he can get as he deserves a good rest. Thanks Troy for all your hard work at keeping our job moving along. I am sure when he sees kitchen handles or basin mixers in Bali, he will think of those 2 annoying blondes Kerith & AJ back in Sydney LOL.

I received a phone call from DiLorenzo yesterday updating me on my delayed main floor tiles. They will arrive in Melbourne on Tuesday and be airfreighted up ASAP. The tilers will be ready to lay as soon as they arrive, I was promised.

Troy sent me a parting screenshot this morning with changes due to the delay in tiles. He mentioned the other rectification works that are scheduled to occur in his absence of 3 weeks.
"I have scheduled works as per the screenshot below. Other works to occur include- tiling behind rangehood, rectifying damaged tile to ensuite shower, rectification works to robes and treatment to isolated staining on bricks. I have am expecting to receive an answer on shortening the shelving to the linen and have left the vanity basin mixer query with Rania." 



Wednesday, August 21, 2013

So exciting!


Wow! The house is looking fantastic. Love, love, love it even without being cleaned or flooring in. We discovered a few issues to fix up.
* The laundry cupboards have been fitted out with shelving when we have put it in the contract to delete it all. The shelving installed is fine though they have not left us anywhere to store ironing board, brooms, mops etc. Troy is going to delete 1/4 of the shelving for that purpose.
* The vanities have incorrect mixers installed. Thanks to AJ for picking that up immediately. They are far too long and, in fact, are bath mixers.
* There is a motion sensor for my WIR missing.

Enjoy the photos.

Powder room vanity

Alarm pad (!)

Study/guest

Formal lounge

Stairs with step lights added

Undermount sink with mixer/vegie spray

Family room

Hallway to front door

My beautiful linen cupboard

Main bathroom (incorrect mixer)

Ensuite bathroom                                  





Ensuite shower
Ensuite bath
Pantry

Pantry

Half the laundry cupboard

Other half

Alfresco fans



Site meeting today

Looking forward to a site meeting with Troy today before he goes on annual leave. Since I have last been to the house we have had electrical fitoff, plumbing fitoff, aircon installed, pantry & linen cupboard fitout and internal painting finished. It may even look a little bit like a home today. Camera ready......

Saturday, August 17, 2013

Friday, August 16, 2013

Hmmm....more wardrobes

But first I'll give you a photo of the house from this week, taken with my phone....



Yesterday I received a Building Contract Variation from my CSA for the amendments to be made as already discussed with Alan from HOG. I had already viewed it on my phone earlier in the day and printed it off when I got home ready to sign, scan and email back. As I signed it, I noticed a line in the NOTES section "10 calendar days will be added to your construction time due to these variations....". No way! An error on their behalf and I am penalised 2 weeks for it?? It wasn't going to happen. I might even offer to accept settlement with the wardrobes unfinished if I needed to meet in the middle but there was little chance of 2 weeks being slapped on the contract for giving wardrobes some extra height.
The lovely Bev rang me today, and amongst chatting about everything else under the sun, she took responsibility for the note on the BCV and apologised. She was asked how long it would take to fix it up, said about 2 weeks but didn't expect it to be added to the contract time by the other staff member. Bev said she should have been a little clearer in her answer. All forgiven here ;-)