MONDAY OCTOBER 21 in the morning
A little disappointed that it couldn't be Friday afternoon to give us the weekend to 'play' in it. It probably comes down to availability to meet onsite too.
The last week has been full steam ahead with PCI, purchasing decorating items, loan settlement, insurances, tying up loose ends and creating other loose ends, on top of being sick and looking after other sick family members. A few more dates have been booked in to the schedule - Shutter/blinds installation October 15 and appliance installation on October 16.
I received an email this morning from EBH informing me that our cooker is out of stock but that they are happy to offer us an upgrade. A Google search revealed nothing on this upgraded cooker so I rang Baumatic in VIC just to ensure we were getting at least a similar product. This cooker has extra capacity and triple rather than double glazed door. I approved the upgrade!
The private certifier has completed his inspection for the occupancy certificates. We have some items that need to be completed
FOR INTERIM OCCUPATION CERTIFICATE
1. Provide a copy of the engineers certificate for glass balustrades confirming that the design complies with AS1170.1 & AS1288-2005
2. Submit compliance certificates
3. Site Cleanup
FOR FINAL OCCUPATION CERTIFICATE
1. Provide a copy of the engineers certificate for glass balustrades confirming that the design complies with AS1170.1 & AS1288-2005
2. Submit compliance certificates
3. Site Cleanup
FOR FINAL OCCUPATION CERTIFICATE
1. Comply with condition 23 with reference to retaining walls
2. Comply with condition 21 with reference to vehicular crossing
3. Comply with condition 20 with reference to driveway installation
4. Repair/Reinstate damaged footpath
2. Comply with condition 21 with reference to vehicular crossing
3. Comply with condition 20 with reference to driveway installation
4. Repair/Reinstate damaged footpath
None of these items seem to be an issue so the certificates should be fairly easy to access.
HnK Ryan has completed their re-inspection which marries up fairly nicely with our PCI inspection report. Troy has indicated that most items identified by the independent inspectors will be fixed anyway but I will use this report as the basis for our 90 day maintenance inspection.