And this is being experienced by a few of my fellow H1 members too. This is more a to-do list for me but these are the things that need following up.
1) Quote for a bulkhead in the laundry 07/08 - not needed according to CSA 16/08.
2) Quote for the change in front doors & rumpus sliding doors to Madison 06/08 - received & accepted
3) Follow through on wardrobe shape in main 02/08 - not needed as will leave as is.
4) Quote for extra aircon vents to the laundry, main bathroom & ensuite 14/08
Also waiting on.....
1) Kitchen, bathroom & laundry 3D drawings from Kitchen Culture 17/07 received 22/08 accepted 22/08
2) Answers from electrical guy to tie that variation up 14/08 (DONE 17/08 - accepted)
3) Details from Di Lorenzo for tiles, carpet & kitchen splashback 14/08
4) Quote from Abbey Blinds though won't hold my breath - someone is still waiting on their quote from NOV 2011!!) 14/08
5) Quote from Genneral Stairs for balustrading 14/08 - received & approved
6) Relocation of gas point from inside to outside 14/08
7) Images of wardrobes from HOG 07/08 Received 24/08
8) Image of standard mirrors from HOG 16/08