I received an email from Troy this morning which included this screenshot of the program for the next 2 weeks. Looks like a lot of it depends on how the painters are going.
Email from Troy.....
"Another good week on site. Tiling to wet areas complete and painting has commenced. We did have a bit of a hiccup with the stone tops to the wet areas having to be replaced because a hole was drilled behind the basins when the taps are wall mounted. They were replaced pretty quick and didn’t hold up progress though.
Did have a complaint from a neighbour re rubbish on site. I explained our policy and procedure regarding rubbish. I had previously scheduled a Yard clean which will occur today. I explained to to the neighbour that we have milestones when rubbish would be removed and it is impractical to have the rubbish removed on a weekly schedule. I also asked if there was any rubbish outside of the site, to which she said “no”. She was purely concerned with the volume of rubbish on site. Just thought I would give you the heads up on this."
Sounds like Troy dealt with the issue. The neighbour is going to have to deal with more building on the other side of her house when it gets developed soon.