EDIT - Now a 'work at the local school' mum a few days a week while juggling the job of parenting 3 teenagers! I am a SAHM who does work from home occasionally, dedicated to raising 3 Godly, independent, healthy children. Loving the home building process though it is not without challenges. I have fairly free reign over the creative aspect of the project...just not the financial side!

Friday, August 2, 2013

Next screenshot


I received an email from Troy this morning which included this screenshot of the program for the next 2 weeks. Looks like a lot of it depends on how the painters are going.

Email from Troy.....

"Another good week on site. Tiling to wet areas complete and painting has commenced. We did have a bit of a hiccup with the stone tops to the wet areas having to be replaced because a hole was drilled behind the basins when the taps are wall mounted. They were replaced pretty quick and didn’t hold up progress though.
 Did have a complaint from a neighbour re rubbish on site. I explained our policy and procedure regarding rubbish. I had previously scheduled a Yard clean which will occur today. I explained to to the neighbour that we have milestones when rubbish would be removed and it is impractical to have the rubbish removed on a weekly schedule. I also asked if there was any rubbish outside of the site, to which she said “no”. She was purely concerned with the volume of rubbish on site. Just thought I would give you the heads up on this."

Sounds like Troy dealt with the issue. The neighbour is going to have to deal with more building on the other side of her house when it gets developed soon.


Tuesday, July 30, 2013

Bubbling along

Everything is happening as per schedule which is nice. I was amazed to see the tilers on site ALL weekend, yes even Sunday. He assured me he was making no noise - just grouting.
Today, we have the floor sanders making a huge mess upstairs. Dust is flying out the windows.
The painters are due to start tomorrow and should be working on the house for the next 2 weeks or so.

Friday, July 26, 2013

Site visit = photo fest

Alfresco tiles

Rangehood, cupboards with THE handles, stonetops

Undermount sink & stonetop

Sink 'run'

Whopping watertank

Powder room vanity

Front door from inside

Main bathroom vanity - part of 3 way bathroom

Ensuite vanity

Ensuite - floor to ceiling tiling

Stackstone is nearly finished
It was rather difficult to talk, measure and take photos at the same time so there aren't too many for you but you get the idea.
Kitchen handles - I think we will leave them for the moment and readdress later down the track if we wish to.
Everything else is looking great. There is a slab issue in the kitchen/family area that is being addressed before tiles are laid (apparently an easy fix)
I am particularly loving the laundry but I was too busy ooh-ing and aah-ing to take a photo. The LONG bench on one side and the double cupboard on the other are amazing!

Thursday, July 25, 2013

A teaser....

Tomorrow's post will contain loads of photos. I am meeting Troy on site tomorrow to check out the progress and the kitchen handles. I am hoping that I will have time to wander around and shoot away. Maybe I can give AJ (re-do my space) those honours whilst I talk to Troy.
The stackstone on the front portico has been started and whilst it looks good, it is darker or 'dirtier' than I thought it would be. Photo to come tomorrow.
I also sent a message to the Wardrobe World installer today as directed by their head office. I am keen to find out the cost to add some more drawers to the wardrobes - 2 is not enough and it seems our wardrobes are too shallow to accommodate any stand alone shelving.



Wednesday, July 24, 2013

Kitchen handle update

 The news has come back from EBH that nothing can be done at this time with the handles.

"Unfortunately I don’t have good news for you. All cabinets, doors and drawers have been installed with the square handles (0115154). As you have found, this is as per the colour selection. The handle that you wish to change to (9112637), will not suit the holes that have been drilled. To change the handle, new doors would need to be made. You may consider changing this after settlement."

Whilst I understand that it was partially my mistake and we signed off on it, there is a part of me that is a little disappointed at the mistake that was made in the first place by the HOG consultant who confesses that she is 'not very good with numbers & letters' or in the words of another blogger 'a self-diagnosed dyslexic'.

One of my fellow Home One members who has both types of handles in his kitchen feels that we can definately do something in the future to rectify the situation even if it means contacting the kitchen supplier to assist. He also had errors in his HOG colour selection sheet.

WARNING to those about to embark on the journey - take photos of everything you select WITH codes visible to assist with crosschecking later down the track. Part of our problem was that we selected our products in July 2012 and didn't receive the final paperwork until January 2013.

Monday, July 22, 2013

Kitchen handle potential disaster

  
Photo courtesy of fellow EBH bloggers Anne & Alok
It has come to my attention over the weekend that we are going to have an issue with our kitchen cupboard handles. I went back to our paperwork and discovered that I had overcorrected a mistake made by Home Options Gallery in the final paperwork. When we received our colour selection sheet, we realised that the incorrect bathroom vanity handles were recorded and alerted our consultant. She changed this manually on our sheet and assured us that it would make it's way onto our final documents. Of course when our final documents came through, they were still incorrect. I changed them to what we had selected (the square ones pictured second from the bottom) but also accidentally overcorrected and changed the kitchen ones to these as well. I am sure they are going to look 'wrong' in the kitchen. At this stage, I am not sure whether they have been added to the cabinets or not. I have Eden Brae looking into the situation for me and i have requested a site visit to check it all out. If they have already been attached, we may have problems with screw holes :-( If only an error had not been made in the first place......