EDIT - Now a 'work at the local school' mum a few days a week while juggling the job of parenting 3 teenagers! I am a SAHM who does work from home occasionally, dedicated to raising 3 Godly, independent, healthy children. Loving the home building process though it is not without challenges. I have fairly free reign over the creative aspect of the project...just not the financial side!

Tuesday, September 3, 2013

Site inspection


I went to the house to find most of the tiling completed. In fact, the tilers told me that they will have completed it today. They schedule 5-7 days but a large team was assigned our job so they have been able to fly through it.

It was great to meet Matt who seems very thorough and organised. I know our home is in safe hands with him. He is, though, going on leave next week for a few days. He is aiming to get the house ready for our Tyrells inspection as soon as Troy returns from leave.

The new things I discovered today were that the towel rails have been incorrectly installed. Standard for our house is a 600mm double rail in the ensuite and an 800mm single rail in the main bathroom. We requested an extra for the main. Unfortunately the 2 800mm rails have been put in the ensuite and the smaller one in the main. We decided to keep the ensuite as is and order another smaller one to add to the main bathroom. Here's hoping EBH don't slap me with a variation for this mistake too ;-)
The cladding on the front of the house has been painted white as per the eaves rather than Mountain Shadow like the render. This needs to be changed.

A busy day at the house all up with tilers, site cleaners and a carpenter there doing touchups.

PS. Oh and the front door handles?? The door aren't hung correctly so when that gets fixed, the handles should be even.

Monday, September 2, 2013

Main floor tiling


It has FINALLY started about 2 weeks after the scheduled time. There was a delay in sourcing them from China so the tilers had to be redirected elsewhere. DiLorenzo kindly have kept me up to speed on what is happening at their end. When I was taking the door photos on Friday, a supervisor from DiLorenzo showed up to inspect the property. He wasn't sure on the latest but assured me that the tilers would be ready to go as soon as they arrived. The tiles must have been delivered over the weekend as the tilers were there first thing this morning. Yay!

Friday, August 30, 2013

Uneven to your eyes too??


Hmmmmm, a little uneven, I think. Can't wait to meet Matt on site next week to check out all the other hardware items that have been installed since my last visit.

Thursday, August 29, 2013

Update on laundry shelving error


Half of the laundry cupboard shelving

Well, it has been an 'exciting' few days in my neck of the woods. I received a Building Variation from EBH to delete 1/4 of the shelving that was erroneously installed. (You may remember, we had it deleted from the contract so we could do a custom fitout to suit our needs) Imagine my surprise when we were charged nearly $700 for the privilege of taking some of it out and adding an end panel in. Surprise was the nice word for it. No explanation via phone call, just an email with a $700 price tag. I asked for clarification  - if I delete the entire amount of shelving, would I be charged anything? NO was the answer! So essentially, I was either being charged $700 for ONE panel of melamine or EBH were trying to recoup the costs of their mistake by charging me for the shelving. A very sour taste has been left in my mouth on this one even though yes, I am getting free shelving (not quite what I want though). After asking a few questions, the Estimating Department has flipped their decision and there will be no charges to cut out 1/4 of the shelving. Yet another mistake, this time not handled well.

On a brighter note, the Temporary Supervisor rang for a chat today - lovely guy. Matt gave me a rundown on what is being done currently and about to happen with the house. The main floor tiles have been delayed further and will now commence early next week. The bath wall mixers will be changed over to the basin wall mixers a little later when the plumbers need to return for something else. Matt reassured me that work will continue smoothly in Troy's absence and will be scheduled ahead for Troy's return. I will try to meet up with him at the house on Monday morning sometime to have another look/see. Before then, I want to go through the contract to see if there is anything we added or deleted, check door handles, towel rails/rings etc, outside taps etc.

Friday, August 23, 2013

And he is OFF!

On holidays! I wish him all the sun and sand that he can get as he deserves a good rest. Thanks Troy for all your hard work at keeping our job moving along. I am sure when he sees kitchen handles or basin mixers in Bali, he will think of those 2 annoying blondes Kerith & AJ back in Sydney LOL.

I received a phone call from DiLorenzo yesterday updating me on my delayed main floor tiles. They will arrive in Melbourne on Tuesday and be airfreighted up ASAP. The tilers will be ready to lay as soon as they arrive, I was promised.

Troy sent me a parting screenshot this morning with changes due to the delay in tiles. He mentioned the other rectification works that are scheduled to occur in his absence of 3 weeks.
"I have scheduled works as per the screenshot below. Other works to occur include- tiling behind rangehood, rectifying damaged tile to ensuite shower, rectification works to robes and treatment to isolated staining on bricks. I have am expecting to receive an answer on shortening the shelving to the linen and have left the vanity basin mixer query with Rania." 



Wednesday, August 21, 2013

So exciting!


Wow! The house is looking fantastic. Love, love, love it even without being cleaned or flooring in. We discovered a few issues to fix up.
* The laundry cupboards have been fitted out with shelving when we have put it in the contract to delete it all. The shelving installed is fine though they have not left us anywhere to store ironing board, brooms, mops etc. Troy is going to delete 1/4 of the shelving for that purpose.
* The vanities have incorrect mixers installed. Thanks to AJ for picking that up immediately. They are far too long and, in fact, are bath mixers.
* There is a motion sensor for my WIR missing.

Enjoy the photos.

Powder room vanity

Alarm pad (!)

Study/guest

Formal lounge

Stairs with step lights added

Undermount sink with mixer/vegie spray

Family room

Hallway to front door

My beautiful linen cupboard

Main bathroom (incorrect mixer)

Ensuite bathroom                                  





Ensuite shower
Ensuite bath
Pantry

Pantry

Half the laundry cupboard

Other half

Alfresco fans



Site meeting today

Looking forward to a site meeting with Troy today before he goes on annual leave. Since I have last been to the house we have had electrical fitoff, plumbing fitoff, aircon installed, pantry & linen cupboard fitout and internal painting finished. It may even look a little bit like a home today. Camera ready......