EDIT - Now a 'work at the local school' mum a few days a week while juggling the job of parenting 3 teenagers! I am a SAHM who does work from home occasionally, dedicated to raising 3 Godly, independent, healthy children. Loving the home building process though it is not without challenges. I have fairly free reign over the creative aspect of the project...just not the financial side!

Tuesday, September 3, 2013

Site inspection


I went to the house to find most of the tiling completed. In fact, the tilers told me that they will have completed it today. They schedule 5-7 days but a large team was assigned our job so they have been able to fly through it.

It was great to meet Matt who seems very thorough and organised. I know our home is in safe hands with him. He is, though, going on leave next week for a few days. He is aiming to get the house ready for our Tyrells inspection as soon as Troy returns from leave.

The new things I discovered today were that the towel rails have been incorrectly installed. Standard for our house is a 600mm double rail in the ensuite and an 800mm single rail in the main bathroom. We requested an extra for the main. Unfortunately the 2 800mm rails have been put in the ensuite and the smaller one in the main. We decided to keep the ensuite as is and order another smaller one to add to the main bathroom. Here's hoping EBH don't slap me with a variation for this mistake too ;-)
The cladding on the front of the house has been painted white as per the eaves rather than Mountain Shadow like the render. This needs to be changed.

A busy day at the house all up with tilers, site cleaners and a carpenter there doing touchups.

PS. Oh and the front door handles?? The door aren't hung correctly so when that gets fixed, the handles should be even.

2 comments:

  1. Hi Kerith,
    I hope you are well.
    I was wondering if Matt, is Matt O'D?

    ReplyDelete
  2. Yes, Matt O'D it is! Why? Is he your SS?

    ReplyDelete