Pool excavation started this morning and by 8am we had received a call to tell us that they had hit rock :-( Peter, the site supervisor, needed me to contact EBH to see if they would use fill with sandstone in it. It took a while for the answer from EBH which of course, was NO!
Peter has measured the rock to be 18.3 m3 with the monetary value of $3.4K for the excavation alone. Depending on how many loads of fill there are, we will now have some cartage/tipping fees too ($1.2K per load)
Peter estimates the excavation will now be finished by Wednesday and with the Australia Day holiday thrown in, it will be more like next Wednesday when they finish as they have a few EBH contracts that they need to start at the same time.
About Me
- Kerith
- EDIT - Now a 'work at the local school' mum a few days a week while juggling the job of parenting 3 teenagers! I am a SAHM who does work from home occasionally, dedicated to raising 3 Godly, independent, healthy children. Loving the home building process though it is not without challenges. I have fairly free reign over the creative aspect of the project...just not the financial side!
No comments:
Post a Comment