EDIT - Now a 'work at the local school' mum a few days a week while juggling the job of parenting 3 teenagers! I am a SAHM who does work from home occasionally, dedicated to raising 3 Godly, independent, healthy children. Loving the home building process though it is not without challenges. I have fairly free reign over the creative aspect of the project...just not the financial side!

Friday, September 13, 2013

Site fencing gone

....portaloo gone and house cleaned. Here are some photos of the exterior. Still some painting to go at the front. The yellowish corbel is to be painted the same colour as the render and the cladding right up the top is to be that colour too.



Thursday, September 12, 2013

I can sniff the end now!

Matt rang tonight to update me on what has happened since we last spoke (and in his absence for 3 days this week). Everything has been done as per schedule though there was something (?) that materials were in short supply for. Timber for wardrobe rectification works? Can't remember what Matt said.
Matt told me that the house clean is still scheduled for tomorrow with Tyrells booked in for Wednesday September 18 and the painters/plasterers ready the following days for touchups. At this moment in time, carpet is due for installation on Monday 23rd though this could get pushed back depending on what is discovered at the Tyrells inspection.

I have been so impressed with Matt and the way he has taken this on board for 2.5 weeks. He has a few extra houses added on top of his workload making him extra busy. We are way ahead of schedule so he could have just let it ride whilst Troy was away. To the contrary! Lots of calls and emails, easy to talk to, organised some things to fix that he noticed were not quite right. Thank you Matt fromt he bottom of our hearts - what a legend!

Wednesday, September 11, 2013

Wood stain

All very quiet on the building front. It looks like someone was there for a few hours on Monday but nothing since. Both supervisors are on leave. Hopefully that means that the job scheduled for Monday/Tuesday has been completed already.

I have been discussing with AJ from re-do my space the colour we selected for our staircase stain. As this occurred 12 months ago, I had no recollection or record of it. All I knew was that it was Taubmans Walnut. Research online and at my local Bunnings proved fruitless. We were desperately hoping that it wasn't too red in tone as the furniture we have bought is more of the chocolate variety. It would be too late to change it as well. Rather than emailing and waiting for a response from Home Options Gallery, I decided to pay them a visit this morning. Phew! Walnut (right hand side) is a nice brown colour and Jarrah (left hand side is the redder one)



Thursday, September 5, 2013

Basin mixers swapped over


Matt sent me a photo tonight of the new mixers that have been placed in all vanities today in lieu of the long (bath) ones - much more practical and pleasing on the eye. Thanks Troy and Matt.

Wednesday, September 4, 2013

Upcoming schedule

Received an email from Matt last night informing me of the items he has booked in to occur at the house.

"Please note the below update of progress and what is booked leading up to Troy's return.
-    Friday 6th, Tilers to complete main floor areas
-    Sat / Mon - Fixing carpenter to return to install Bed room smart robe door units, and a few other items per my inspection list
-    Bed 3 Ceiling, requires repair over the internal door, as there is a slight undulation, Frame carpenter booked to return Mon / Tues to rectify
-    Plastering contractor booked for Thurs 12th to meet with myself / to complete defects as marked, Cornices to garage, Bed 3 ceiling repair.
-    House cleaner Initial clean - Friday 13th.
As discussed, I will also be on annual leave Monday 9th to Wed 11th, however the above items have been booked / confirmed to be carried out."


I think the tilers might have finished already if everything went according to plan yesterday. The site was cleaned (sort of) today - there still seems to be a lot of junk lying around?? My latest screenshot has the site fencing being removed tomorrow. I hope the house is locked up a little more securely than it has been from now on.

Tuesday, September 3, 2013

Site inspection


I went to the house to find most of the tiling completed. In fact, the tilers told me that they will have completed it today. They schedule 5-7 days but a large team was assigned our job so they have been able to fly through it.

It was great to meet Matt who seems very thorough and organised. I know our home is in safe hands with him. He is, though, going on leave next week for a few days. He is aiming to get the house ready for our Tyrells inspection as soon as Troy returns from leave.

The new things I discovered today were that the towel rails have been incorrectly installed. Standard for our house is a 600mm double rail in the ensuite and an 800mm single rail in the main bathroom. We requested an extra for the main. Unfortunately the 2 800mm rails have been put in the ensuite and the smaller one in the main. We decided to keep the ensuite as is and order another smaller one to add to the main bathroom. Here's hoping EBH don't slap me with a variation for this mistake too ;-)
The cladding on the front of the house has been painted white as per the eaves rather than Mountain Shadow like the render. This needs to be changed.

A busy day at the house all up with tilers, site cleaners and a carpenter there doing touchups.

PS. Oh and the front door handles?? The door aren't hung correctly so when that gets fixed, the handles should be even.

Monday, September 2, 2013

Main floor tiling


It has FINALLY started about 2 weeks after the scheduled time. There was a delay in sourcing them from China so the tilers had to be redirected elsewhere. DiLorenzo kindly have kept me up to speed on what is happening at their end. When I was taking the door photos on Friday, a supervisor from DiLorenzo showed up to inspect the property. He wasn't sure on the latest but assured me that the tilers would be ready to go as soon as they arrived. The tiles must have been delivered over the weekend as the tilers were there first thing this morning. Yay!