About Me

My photo
EDIT - Now a 'work at the local school' mum a few days a week while juggling the job of parenting 3 teenagers! I am a SAHM who does work from home occasionally, dedicated to raising 3 Godly, independent, healthy children. Loving the home building process though it is not without challenges. I have fairly free reign over the creative aspect of the project...just not the financial side!

Sunday, June 16, 2013

Highly recommended product.....

http://www.aussieskipbags.com.au/

Wow! The customer service is impeccable.  In clearing out our current home, I needed somewhere to DUMP 11 years worth of stuff that we no longer need. I had heard about this company from others on the forum I frequent. I thought it was worth a go rather than having a metal skip bi sitting on the driveway and paying for its hire.
I logged my request at 12pm one day and it was on my doorstep by 3pm the same day. I easily filled it up and yesterday logged a pickup. It suggests a 5 day turnaround but at 1pm today the truck was here to collect the bag.
The only issue I had was of course, my bag wasn't big enough!!

Friday, June 14, 2013

Photos of the rear of the house

Again, my lovely neighbour has pointed his camera over his fence to take photos for us. Looks like the cladding at the back is still to be installed.
Nearly half way with the pool levels. A little chlorine and we'll be right!










Thursday, June 13, 2013

Lower roof completed





Lower roof done today. Most of it is out the rear of the house which is a no access zone  - sorry, no photos.
I received my Building Variation today for the airconditioning changes to be made as per yesterdays visit. One half of it (the ground floor ceiling height change) was left off the paperwork. I alerted Rania who will amend this Variation before I sign it.
Howard Ryan called today to finalise his independent inspection time and payment for next Thursday late afternoon. He does this first inspection prior to internal linings/lockup.

Wednesday, June 12, 2013

Vanity idea??!!



I met Troy on site today but forgot to ask him if Eden Brae can get our vanities hooked up like this. I heard they also come in white! Cool idea.

I met Troy to discuss some issues with airconditioning. At the plumbers/Troy's suggestion earlier, we moved the hot water service to the media room wall to help with efficiency. In fact, it was moved to the family room external wall right where the outdoor airconditioning unit is to be positioned. I agreed that it was OK to be moved to the media room wall instead. In fact, we agreed it would probably be better there anyway - less noise in the area we will spend the most.
We also have a few issues with the ducting coming downstairs to the living areas mainly due to the structural changes we made. When I ask for changes and they get approved, I assumed all aspects had been looked at to ensure it works. Um NO! As of today, we will now lose a corner of BED2 for ducting and the powder room, WC and mudroom area will have the roof lowered to standard height to enclose some ducting. Not particularly happy about it but they are our best options now.

Whilst I was there, we had the airconditioning roughin happening and the roofing had started. Torrential rain saw the roofing guys shut up shop. Lockup should be in about 2 weeks time and the gyprock will begin.

Tuesday, June 11, 2013

Screenshot for this coming week

Finally some major action on site scheduled though rain IS forecast tomorrow

Troy also wants to meet up on site to discuss aircon vents. Name the time & I'm there!

On our current home, it is all action here. I sorted out the childrens' rooms today and started filling my Aussie Skip Bag sitting on the driveway. I am meeting with the handyman tomorrow and the new carpet is booked in to be laid next Monday. Not much rest here until the removalists have been next Wednesday

Wednesday, June 5, 2013

As promised....

....the fascia and guttering for the lower storey has been installed this morning but not really photo worthy.

The last few days have seen me busy trying to get things organised for a 'potential' buyer to look through our current house. Vanity purchased, handyman organised, boxes and storage organised, contract of sale ordered with conveyancer (with a mid November settlement date), carpet to be purchased tomorrow and hopefully installed next week. Very busy times ahead! Now to hope that EBH don't have major issues and go over the contract end date. Early is FINE with us - more time for landscaping, pool etc.

Tuesday, June 4, 2013

Very quiet on site

....so I sent an email to Troy to see if what the reason was. I was still waiting on a reply to an email I sent on the weekend regarding possible damage to the house/site following our unwanted visitors on the weekend. The reply I received went like this :-

"There were some issues with material supply (fascia was scheduled for 31st May). Fascia and gutter will now be installed tomorrow with roof rail and roofing to follow. Given this all goes to plan, we will not have lost any time, just compressed the window that they would normally have to carry out the installation. Thanks."

I am still not sure where the external painters disappeared to?? Maybe the revised plan is to do upper & lower storeys at once